Installing central heating from scratch: the order of work

A new heating system is mostly a design job. By the time anyone lifts a floorboard, every radiator size should already be decided.

Gas Safe registered (554328) Worcester Bosch accredited Free, no-obligation quotes

Full central heating installations happen in three situations: a property that has never had it, a renovation stripped back to bare walls, and an existing system so old and corroded that replacing the pipework is more sensible than nursing it.

Unlike a boiler swap, the appliance is almost the last decision. Everything ahead of it — room-by-room heat loss, radiator sizes, pipe layout, zoning and controls — determines whether the finished system is quiet and efficient or noisy and unbalanced.

The order the work happens in

  1. 1

    Room-by-room heat loss

    Every room calculated from its construction, glazing and exposure. This produces the radiator sizes and the total system load.

  2. 2

    Emitter selection

    Radiator sizes and types chosen to meet each room's load — ideally at a lower flow temperature, which improves boiler efficiency.

  3. 3

    Pipe layout design

    Where the mains run, how branches reach each radiator, and whether the design is two-pipe throughout with sensible index circuit lengths.

  4. 4

    Zoning and control strategy

    How many zones, where the thermostats go, whether weather compensation is being used, and how hot water is controlled.

  5. 5

    Boiler and cylinder choice

    Selected to suit the calculated load and hot water demand — the consequence of the design, not the starting point.

  6. 6

    First fix pipework

    Floors up, pipe run and clipped, notching done correctly, radiator tails positioned, pressure tested before anything is covered.

  7. 7

    Second fix

    Radiators hung, valves fitted, boiler installed and connected, controls wired, condensate and flue completed.

  8. 8

    Fill, clean and dose

    System filled, cleansed, flushed, then dosed with inhibitor and the filter fitted.

  9. 9

    Commission and balance

    Boiler commissioned with readings taken, then every radiator balanced so flow is shared properly across the whole system.

Why balancing is not an optional final flourish

Water takes the easiest path. Without balancing, radiators nearest the boiler take more than their share of flow and the far end of the circuit runs lukewarm — the classic "upstairs back bedroom is always cold" complaint that no amount of bleeding will fix.

Balancing sets the lockshield valve on each radiator so every emitter gets the flow its size requires, measured by temperature difference across it. On a new system it should be done at commissioning as a matter of course, and it is the single most common omission we find on installations carried out by others.

Decisions worth getting right at design stage

  • Radiator sizing generous enough to run lower flow temperatures — better efficiency now, and heat pump readiness later
  • Zoning that reflects how the house is used, rather than one thermostat in a draughty hall
  • Whether towel rails are on the heating circuit, and how they behave in summer
  • Pipe routes that avoid future floor damage when maintenance is needed
  • Provision for a magnetic filter in an accessible position
  • Drain points at the low ends of the system so future flushing is straightforward

How long a full installation takes

PropertyTypical durationWhat drives it
Two bed flatAround 3–4 daysShort pipe runs, few emitters, limited floor access
Three bed semiAround 4–6 daysTwo floors of first fix pipework and making good
Four bed detachedA week or moreMore emitters, zoning, possibly a cylinder installation
Renovation projectPhased around other tradesFirst fix before plastering, second fix after decoration

Durations are indicative — access, floor construction and whether the property is occupied all change them.

The quality of a heating system is fixed long before anyone turns it on: heat loss calculated properly, radiators sized honestly, pipework laid sensibly, and every emitter balanced at the end. Get that sequence right and the system simply works, quietly, for decades.

Questions people ask

Can central heating be installed without lifting every floor?

Rarely entirely, but routes through voids, lofts and existing pipe runs reduce it considerably. Solid concrete ground floors are the main constraint, and are often served by dropping from above or surface-run pipework in trunking.

Should radiators be sized larger than needed?

Slightly generous sizing is a good thing. It lets the system deliver the same heat at a lower flow temperature, which improves condensing efficiency and makes a future low-temperature system far easier.

Is underfloor heating worth including in a new system?

It works very well on ground floors, particularly in renovations where floor build-up can be planned. It is usually combined with radiators upstairs rather than used throughout.

Does a new system need cleaning if the pipework is new?

Yes. New pipework carries flux, swarf and installation debris, so a cleanse before dosing with inhibitor is standard practice on brand new systems as well as replacements.

Discuss a full central heating installation

We start with room-by-room heat loss and radiator sizing, then design the pipework and controls around how your household actually uses the property.

New central heating pipework being installed beneath a lifted floor

Who does the work

  • Gas Safe registered engineers — registration 554328
  • Worcester Bosch accredited installer
  • John The Plumb Ltd, company registration 10026483

Keep reading

Related service
Central heating services
Visit central heating hub
WhatsApp
Call nowFree quote