Get in touch 07891 410 960
What to expect

Bathroom fitting: what happens and how long it takes

A bathroom fit is a sequence, and each stage waits on the one before. Knowing the order makes the disruption easier to plan.

Gas Safe registered (554328) Worcester Bosch accredited Free, no-obligation quotes

Fitting a bathroom follows a fixed order: strip out the old suite and tiles, alter the pipework and waste, prepare the walls and floor, fit the bath or shower tray, tile, then fit the toilet, basin, taps and accessories and finish with sealing and testing. How long it takes depends mainly on how much pipework moves, whether a wet room or tanking is involved and how much tiling there is, so the timescale is set at the survey rather than guessed in advance.

Here is what each stage involves and how to make the weeks at home easier.

The order of work

  1. 1

    Protection and strip-out

    Routes through the house are protected, water is isolated and the old suite, tiles and boards come out.

  2. 2

    First fix

    Supply and waste pipes are altered or renewed, shower valves set into the wall and any electrics for lights or fans run.

  3. 3

    Walls and floor

    Boards replaced where needed, walls lined or boarded, and wet areas tanked for waterproofing.

  4. 4

    Tray or bath

    Fitted level and secure before tiling so tiles can finish neatly over the edges.

  5. 5

    Tiling and grouting

    Usually the longest single stage, with drying time before grouting.

  6. 6

    Second fix and finish

    Toilet, basin, taps, shower, towel rail and accessories fitted, silicone applied and everything tested for leaks.

What makes it take longer

FactorWhy it adds time
Moving the toiletWaste pipe rerouting, sometimes under the floor
Walk-in or wet roomTanking and curing before tiles go on
Full-height tilingMore area and more cutting around fittings
Concealed cisterns and valvesFraming and boxing before walls are finished
Surprises at strip-outRotten boards or old pipework to replace
Waiting on itemsMissing parts stop the sequence

Living without a bathroom

If it is your only bathroom, ask whether the toilet can be kept working or refitted temporarily at the end of each day during the early stages. That is often possible until the floor is being done.

Dust is worst during the first two days, when tiles and boards come off. Closing the bathroom door, sealing the gap underneath and keeping a window open in the room itself makes a noticeable difference to the rest of the house. Water may also be off for short spells during first fix, while supply pipes are altered, so filling a kettle and a few bottles in the morning saves frustration later in the day.

Silicone needs time to cure before the shower is used, and some tile adhesives and grouts need a day before they are wet. The last day of the job is often not the first day you can shower — worth knowing when you plan around it.

How to prepare

  • Have every item on site before work starts, and check boxes for damage.
  • Empty the room, including the airing cupboard if the cylinder is nearby.
  • Agree where tools and waste will be kept.
  • Plan for dust and noise on the strip-out days.
  • Confirm who is doing electrics and decoration.

Order everything early and check it the day it arrives. A bathroom that starts with every part on site is the one that finishes when it was planned to.

Questions people ask

Can I use the toilet while my bathroom is being fitted?

Often for part of the job. Ask whether it can be reconnected at the end of each day until the floor stage.

Why do bathroom fitters need everything delivered first?

Valves, wastes and trays have to be fitted in order. A missing part can hold up the whole sequence.

When can I use the shower after fitting?

Once the silicone has cured, which is normally at least a day. Your fitter will tell you the time for the products used.

Does a bathroom fitter do the tiling and electrics?

Tiling is usually part of the job. Electrical work in bathrooms must be done or checked by a qualified electrician, so confirm who is responsible.

Getting a bathroom fitted?

Call 07891 410 960 to arrange a survey, a written price and a realistic timescale.

Bathroom mid-installation with new pipework and boarded walls

Who does the work

  • Gas Safe registered engineers — registration 554328
  • Worcester Bosch accredited installer
  • John The Plumb Ltd, company registration 10026483

Keep reading

Related service
Bathrooms
Visit bathrooms hub
WhatsApp
Call nowFree quote